External Infrastructure

Power: 220 KV dedicated powerline to the port area has been initiated by KSEB.


Water: Water supply for the project including treatment plant with 3 MLD capacity also been entrusted to Kerala Water Authority. The tender has been finalised and work to start on month of februery 2012.


Road: Construction of 2 KM connecting road from NH byepass to the port is in progress. Land acquisition for the Road has been completed.


Rail: The draft DPR has been submitted by Rail Vikas Nigam Limited. First round of discussion was held at Trivandrum on 31/12/2011. RVNL has requested to conduct further studies on the rail alignment.